Our projects across Australia

A Team of Experts in Piping System Installation

A team of experts in piping system installation

We pride ourselves in the extensive experience that we have which supports our company and our services. We have had the opportunity in the past to be a part of numerous projects across Australia and continue to bring our expertise and service to projects today.

Our previous projects

Appin Electro-fusion

Principle: BHP


Duration: Aug 2017 - Sep 2017


Role: Contractor


Asia Pacific Piping Systems, in partnership with Georg Fisher, have supported a civil contractor with the installation and testing of three 1 000-millimetre Electro-Fusion couplers. This project required highly skilled personnel and specialised tooling to perform the works in tight, congested trenched areas.

Appin Electro-fusion
Greater Brockman

Greater Brockman

Principle: Rio Tinto


Duration: Nov 2017 - Mar 2018


Role: Subcontractor


Pit de-watering and accompanying 14-kilometre pipelines across multiple sites installing PN16 110 millimetre to 250-millimetre HDPE throughout. Works included five de-watering bores, earthworks, pipeline installation, hydro-testing, Brownfield’s tie-ins, and service commissioning.

Parraburdoo Bores

Principle: Rio Tinto

Duration: Dec 2017 - Jan 2018

Role: Subcontractor

Installation, hydro-testing, and associated earthworks for 3.2 kilometres of PN16 HDPE in 160 millimetre and 250-millimetre diameters. The undertaking incorporated haul road, creek, and light-vehicle crossings in addition to tie-ins of existing tanks and bores.
Parraburdoo Bores
Yandi Centrals

Yandi Centrals

Principle: Rio Tinto

Duration: Nov 2017 - Dec 2017

Role: Subcontractor

Connection and installation of 2 kilometres of PN16 HDPE pipe ranging from 50 to 200 millimetres for the upgrade of plant infrastructure. The project was completed within a Brownfields area involving live plant and associated shutdowns. The scope also included 18 road crossings, earthworks, hydro-testing concerning potable, fire, and process water.

WTS Fire Repairs

Principle: Rio Tinto

Duration: Nov 2017 - Mar 2018

Role: Subcontractor

Extensive repairs and rectification work after widespread damage to major infrastructure assets in the Tom Price region and WTS mine site due to fire. Works included the removal of damaged pipelines and fittings, clearing and grading corridor for re-installation, pipe welding, and tie-ins.
WTS Fire Repairs
Tom Price

Tom Price

Principle: Rio Tinto


Duration: Nov 2017 - Mar 2018


Role: Subcontractor


By working closely with key mining and operations stakeholders at Tom Price mine, APPS completed and restored services on time and with an exemplary safety record. These works were complete in conjunction with the WTS fire repairs.

Yandi Spinifex

Principle: BHP

Duration: May 2017 - Jun 2017

Role: Subcontractor

Connections of new chlorination plant, water discharge pump, existing pipelines, and infrastructure. The scope included HDPE welding, labour, equipment, and auxiliary tooling for the installation of DN50-DN160 COEX pipe, electro-fusion fittings, and live tie-ins within proximity to existing power, services, and other infrastructure.
Yandi Spinifex
Browns Range

Browns Range

Principle: Northern Minerals


Duration: May 2017 - May 2017


Role: Subcontractor


Installation of 14 kilometres of 125-millimetre and 160- millimetre HDPE pipelines connecting two bores to pilot plant and dosing tank. Provision of specialised HDPE welder and equipment, supporting plant operator for work in arid challenging remote location. Completion of scope ahead of planned schedule and under budget.

Yandi Anfo

Principle: Rio Tinto

Duration: Apr 2017 - May 2017

Role: Subcontractor

Upgrade of existing HDPE and copper potable water systems and piping infrastructure. Live dig ups and tie-ins near ammonia nitrate plant servicing fire suppression systems and eye wash stations. Works also included testing and chlorination of the newly installed pipework. Pipe sizes ranged from 25 millimetre up to 63 millimetres.
Yandi Anfo
Western Turner

Western Turner

Principle: Rio Tinto

Duration: Feb 2017 - Oct 2017

Role: Subcontractor

Construction of 450-millimetre to 160-millimetre PN20 pipe network for connection with 7 bores. Scope of works includes the installation of 2 LV stands, haul road crossings, in-pit works and asbestos works. Subcontract supply of HDPE welding crews, supporting multi-licensed operators, HDPE welding equipment and specialised tooling.

Hope Down 4

Principle: Rio Tinto


Duration: Jan 2017 - Mar 2017


Role: Subcontractor


Installation of 355- millimetre SDR9 over 2.5 kilometres HDPE waste fines pipeline for three in-pit slurry droppers. The scope included live tie-ins to existing steel pipework, 110 millimetre and 250millimetre piped crossings at haul road culverts, supporting earthworks for LV/HV ramps at crossings, 710-millimetre culverts, containment ponds and hydro testing.

Hope Down 4
Yandi Project

Yandi Project

Principle: Rio Tinto

Duration: Dec 2016 - Feb 2017

Role: Subcontractor

Construction of 1 kilometre of 355-millimetre HDPE pipeline near existing live infrastructure and other active work fronts. Construction included live tie ins to existing 900 metre pipelines and installation of subsequent offtakes. Subcontract supply of HDPE welder, operator, and supporting plant and equipment.

Silver Grass

Principle: Rio Tinto

Duration: Oct 2016 - Oct 2016

Role: Subcontractor

Installation of three LV pipe stands to existing pipelines and infrastructure. Supply of experienced pipeline welder, supporting labour, and specialised equipment/tooling on a subcontract basis to our client for the performance of works.
Silver Grass
Eastern Ridge

Eastern Ridge

Principle: BHP

Duration: Sep 2016 - Nov 2016

Role: Subcontractor

Provision of experienced subcontract labour as part of the site dewatering team. Labour hire of site qualified and VOC’d multi-licensed operator for integration into client’s project team.

West Angelas

Principle: Rio Tinto


Duration: Aug 2016 - Jan 2017


Role: Subcontractor


Installation of 17 kilometres HDPE pipeline ranging from 450- millimetres to 160- millimetres bore trailer connections, LV/HV standpipes, turkeys nest pipe work & pumps and Hydro testing. Provision of subcontracting services including Superintendent, HDPE welders, operator’s, plumbers, pipefitters, plant and equipment, servicing, and procurement.

West Angelas

Send a Message

Contact Us Today

If you’re in need of piping systems installation expertscall our team today. Fill out our enquiry form and a member of our team will be in touch with you as soon as possible.

Follow Us